Metal Carved Panel Installation Method: Five Easy Steps To Renovate Your Exterior Wall

Author: Site Editor     Publish Time: 2026-05-12      Origin: Site

Inquire

Metal Carved Panel Installation Method: Five Easy Steps To Renovate Your Exterior Wall

Metal carved panels, as a new type of building material integrating heat insulation and decoration, have become an ideal choice for upgrading the exterior walls of modern buildings due to their superior thermal insulation performance and realistic decorative effect. Proper installation is key to maximizing their performance, and can be completed in just five simple steps.


I. Preparation Stage


Once the boards and accessories arrive on site, all necessary installation tools must be prepared in advance: expansion bolts (for concrete or brick walls), dovetail nails (for steel structures), a hand drill, a marker, a measuring tape, a rubber mallet, and a cutting machine. Having sufficient tools prepared can prevent construction interruptions and improve efficiency.


II. Installation Accessories Base


Before installing the panels, first install the bases for the starting pieces, finishing pieces, edging, center seams, and inside and outside corners. These bases may seem insignificant, but they determine whether the panels will be perfectly level and leak-proof. Use a marker to mark the positions, drill holes and fix them in place, then gently tap with a rubber mallet to ensure they are level.


III. Installing the panels


After securing the accessory base, install the first metal carved panel horizontally from top to bottom, ensuring the female end faces down and the male end faces up. Secure with expansion screws or dovetail nails, ideally one nail every 60 cm. Next, align the female end of the second panel with the male end of the first panel and insert it firmly downwards. Gently tap the joint with a rubber mallet to ensure a tight seal before securing the subsequent panels. If the wall dimensions do not match the panel size, on-site measurement and cutting are required before installation.


IV. Install accessory cover plate


After all the panels are installed, press the accessory cover firmly onto the base. Accessories of the same material can be fixed to the wall with screws, and finally sealed with waterproof silicone sealant. This step effectively prevents water seepage caused by thermal expansion and contraction, creating a secondary seal for protection.

9bc2c9ac8bf7ca317e391bac8b17d10a

5. Remove the protective film.


The panels are covered with a protective film at the factory to prevent scratches during handling. Remove the protective film after installation to reveal a refreshed and aesthetically pleasing finish. It is recommended to install on a cloudy day or in the evening to avoid direct sunlight that could leave adhesive residue.


Kind tips


The wall surface should be flat and firm, with a flatness control within 3mm/m; the expansion screws should be driven into the wall to a depth of ≥5cm; construction should be suspended on rainy days, and the panels should be placed vertically to avoid rain. By following the above steps, the metal carved panels can be firmly installed on the exterior wall, achieving both excellent thermal insulation performance and high aesthetic appeal.


Tel
+86-15650586058
+86-18653186482
Our Address
Jixiang Village Industrial Park, Zaoyuan Street, Zhangqiu District, Jinan City, Shandong Province
About us
If you have any questions, please send an email and we will reply to your email as soon as possible.
Subscribe
Sign up for our newsletter to receive the latest news.
​Copyright © 2025 Shandong Yansheng Engineering Materials Co., Ltd. All Rights Reserved.​​​​​​​ Sitemap